FCC Extends Wave 1 Negotiations Extension
The FCC extended the mandatory negotiation period for NPSPAC licensees from July 31, 2006 to October 31, 2006.
The revised timelines are shown below.
Mandatory Negotiations: May 1, 2006 - October 31, 2006
Alternative Dispute Resolution: November 1, 2006 - December 14, 2006
The FCC also indicated that this extension would not affect the overall schedule and deadlines fir the 800 MHz Reconfiguration (although it is hard to still believe that more extensions will not follow for other waves/stages).
The revised timelines are shown below.
Mandatory Negotiations: May 1, 2006 - October 31, 2006
Alternative Dispute Resolution: November 1, 2006 - December 14, 2006
The FCC also indicated that this extension would not affect the overall schedule and deadlines fir the 800 MHz Reconfiguration (although it is hard to still believe that more extensions will not follow for other waves/stages).